Week 17, 05th May to 10th May 2009

Programme:
Excavation at base of site up to Princes Drive.
Kerbing and flagging in the bell mouth from Station Road to the alleyway between Station Road and Penrhyn Road.


Work Activity:    

Mon
Bank holiday
    
Tues
Flagging in roadway outside World Choice and directly outside New Look and the empty bar alongside.Excavation at the base of the site in the immediate vicinity of the junction of Station Road and Princes Drive.

Wed
Radius kerbing laid in the bell mouth between Station Road and the alleyway between Station Road and Princes Drive.

Flagging outside empty bar next to New Look.

Kerbing commenced at the base of the site.
    
Thurs
Kerbing at base of site continued.Flagging in the bell mouth of the alley entrance.

Fri
Flagging outside Manshop and grouting from Arundales down.

Sat
Flagging outside Manshop and Eateasy.

Sun
Flagging outside Manshop and Eateasy.

Next Week’s Programme:
Flagging in roadway from RSPCA down.
Reinstatement to HDM level at the base of the site.