Station Road Week 12
8th October 2009
Weekly Update and Progress Report
Week 12, 30th March to 04th April 2009
Programme:
Connections for the lighting columns.
Excavation outside of Bet Fred, Boxcellence and half of W H Smith.
Reinstatement to flagged level outside above.
Excavation and flagging outside Spar.
Work Activity:
Mon
Flagging between Peacocks and Spar.
Manhole construction outside Central Public house and Help the aged.
Excavation outside of Bet Fred, Boxcellence and half of W H Smith’s entrance took place during the night in order to re-instate before they open in the morning.
Tues
HDM layer laid outside Bet Fred, Boxcellance and half of W H Smiths.Flagging from Peacocks to Spar grouted along with the area from the Central Public house to Bet Fred.
Flagging outside Spar.
Wed
Lighting power connection contractor on site to make connections.Excavation outside empty premises next to W H Smith, half of M & Co and Spar entrance.
Thurs
Flagging from Bet Fred to Boxcellence.
Fri
Flagging past Boxcellence entrance down site.Lantern heads placed on lighting columns.Reinstatement to HDM level outside second half of W H Smith and empty premises next door.
Sat
Flagging in road way from the end of the Central Public House.
Next Week’s Programme:
Flagging in road way and outside W H Smith, empty premises next door and Spar entrance.