Station Road Week 11
8th October 2009
Weekly Update and Progress Report
Week 11, 23rd March to 29th March 2009
Programme
Lighting column construction.
Flagging outside Peacocks, Help the Aged and Central Public House.Excavation outside other half of Peacocks entrance down to entrance of Spar.
Work Activity:
Mon
HDM contractors on site to plane off a high spot of HDM between M & Co and the RSPCA shop.
Tues
Flagging outside Peacocks and grouting of flagged areas.Gully and manhole construction at base of ACO channel.
Wed
Continued flagging outside of Peacocks and the Central Public House.
Thurs
6 lighting columns erected.
Excavation commenced between Peacocks entrance and Spar.
Fri
Sub-base and HDM laid in the excavated areas between Peacocks and Spar.Flagging outside Central Public House.
Sat
Flagging between Peacocks and Spar.
Sun
Area directly outside entrance to Help the Aged excavated and re-instated to flag level.
Connections for the lighting columns.
Next Week’s Programme
Excavation outside of Bet Fred, Boxcellence and half of W H Smith.Reinstatement to flagged level outside above.Excavation and flagging outside Spar.