Station Road Week 10
8th October 2009
Weekly Update and Progress Report
Week 10,16th March to 21st March 2009
Programme:
Flagging at top of site.
ACO channel construction.
Rising bollard casing and induction loop construction.
Work Activity:
Mon
Soft /wet spot excavated in road way between the Imperial and Eateasy.
Flagging continued from last week at top of site.
Tues
Excavation for the ACO drainage channel at base of site.
Flagging at top of site.
Wed
Excavation commenced directly outside Help the Aged and half of Peacocks entrance.Continued excavation for the ACO channel and new manhole connection to drainage system.
Sub-base and HDM layers laid outside Help the Aged and Peacocks.
Thurs
Flagging commenced directly outside Help the Aged and Peacocks.
Fri
Continued flagging outside Help the aged and Peacocks.
Excavation and reinstatement outside Central Public House.
Sat
Tree pit construction outside the Central Public House.
Next Week’s Programme:
Lighting column construction.
Flagging outside Peacocks, Help the Aged and Central Public House.
Excavation outside other half of Peacocks entrance down to entrance of Spar.


News
