Station Road Update
{X3Jlc2l6ZTp3aWR0aDoyODA6aGVpZ2h0OjI4MDpzY2FsZW1vZGU6Zm9yY2U6}.jpg)
Two stages of the Colwyn Bay Town Centre refurbishment scheme are now complete
The
third stage, Station Road, will commence in January 2009 and includes
new paving, street furniture, improved lighting and trees. Once
complete vehicular access on Station Road will be restricted to
permitted times with ‘Rise and Fall’ bollards in place to control
traffic. This will give pedestrians peace of mind to stroll Station
Road at their leisure. The work is scheduled to take 20 weeks.
The £1.5m Streetscape development is an exciting plan where, over 2 years, three distinct phases of work will transform the town centre.
The scheme received nearly £1.25m from the Welsh Assembly Government.
More...
- Station Road Week 1
- No delay was experienced with the site clearance
- Station Road Week 2
- Work continue's on Station Road
- Station Road Week 3
- No delay was experienced with the site clearance
- Station Road Week 4
- Excavation for ACO channels from Peacocks down
- Station Road Week 5
- The sub-base level of construction was laid from the top of the job in the central area and trimmed back to the correct level and rolled.
- Station Road Week 7
- Formation level parallel to Boots graded and Terram and Geo-grid layers laid.
- Station Road Week 8
- Excavation continued from last week of the tree pit areas.
- Station Road Week 9
- Flagging re-commenced at the top of the site (Central Public House end
- Station Road Week 10
- Soft /wet spot excavated in road way between the Imperial and Eateasy
- Station Road Week 11
- HDM contractors on site to plane off a high spot of HDM between M & Co and the RSPCA shop.
- Station Road Week 12
- Excavation outside of Bet Fred, Boxcellence and half of W H Smith.
- Station Road Week 13
- Flagging outside Central Public House and empty premises next to W H Smith
- Station Road Week 14
- Excavation outside Homeland, World Choice and QS.Flagging outside M & Co, William Hill and Homeland.
- Station Road Week 16
- Flagging outside The Central.Grouting outside RSPCA, Arundales and Fair Trade Flooring.
- Station Road Week 17
- Excavation at base of site up to Princes Drive.
- Station Road Complete
- All stages now complete no snagging issues