Greenfield Road Week 9
8th October 2009
Senior Engineer's Update (Conwy County Borough Council)
Week 9 – Phase 3 & 4 Works Week beginning 07th November 2007
Colwyn Bay Streetscape Improvements – Greenfield Road
Phase 2 The tree guard has been fitted, this area is now complete.
Phase 4 The electrical connections have been completed this week as has the paving in the immediate area of the connections.
Phase 4 is now completed.
Phase 3 Phase 3 works have progressed well this week with the paving and all pointing being completed.
All Phases: The road surfacing took place overnight on Wednesday evening, the road markings have been started today (9th November) and will be completed on Monday 12th November..
All phases are now completed save for the installation of new lighting columns: the contractor is still waiting for delivery of the new units.
The contractor has already installed all necessary electrical connections and foundations in readiness for delivery – this is to minimize disturbance to the completed works at a later date.
The contractor has completed the scheme three weeks behind schedule


News