Greenfield Road Week 6

8th October 2009

Senior Engineer's Update (Conwy County Borough Council)

Colwyn Bay Streetscape Improvements – Greenfield Road

Week 6 – Phase 1, 2 & 4 Works - Week beginning 15th October 2007

Phase 1 - The new signs have now been put up on Phase 1

Phase 2 - At this point the contractors are still waiting for delivery of the tree in order to complete this phase.

The pedestrian refuge (crossing island) kerbs are installed, as are new lighting bollards.

The refuge will be paved next week.

Phase 4 - The paving has now extended down to the lower vehicle access to Greenfield Garage.

Both vehicular accesses to the garage have been surfaced with tarmac.

The pedestrian refuge (crossing island) kerbs and new bollards have been installed.

The contractor advises that he is approximately two and a half weeks behind schedule at this point.